Retaining structures to protect the sports field at the elementary school Polhov Gradec

Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-2-Geoportal
Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-2-Geoportal
Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-1-Geoportal
Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-1-Geoportal
Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-5-Geoportal
Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-5-Geoportal
Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-6-Geoportal
Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-6-Geoportal
previous arrow
next arrow
Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-2-Geoportal
Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-1-Geoportal
Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-5-Geoportal
Retaining-structures-to-protect-the-sports-field-at-the-elementary-school-Polhov-Gradec-6-Geoportal
previous arrow
next arrow
Investor

MUNICIPALITY DOBROVA – POLHOV GRADEC, Stara cesta 13, 1356 Dobrova

Investment value

INR 2.91 Crore

Project documentation

BUILDING PERMIT DESIGN, FINAL DESIGN

year of completion

2019

characteristics of the faculty

The supporting structure with a height of 5 m in the complex hydro – geological conditions: permo-carboniferous weathered rock (slate, alevorilit, sandstone, and conglomerate).
Project solution: anchored pile wall with a regulated draining.

Retaining wall was constructed as anchored pile wall. Pile length 10 m, pile diameter 0.8 m, distance between piles 1.6 m. 17 m long ground anchors were installed at top at a horizontal distance of 3.2 m.