Refurbishment of The Karavanke Railway tunnel

Karavanke-Railway-Tunnel-1-Geoportal-e1569177401469
Karavanke-Railway-Tunnel-1-Geoportal-e1569177401469
Karavanke-Railway-Tunnel-2-Geoportal-e1569177330870
Karavanke-Railway-Tunnel-2-Geoportal-e1569177330870
Karavanke-Railway-Tunnel-3-Geoportal
Karavanke-Railway-Tunnel-3-Geoportal
previous arrow
next arrow
Karavanke-Railway-Tunnel-1-Geoportal-e1569177401469
Karavanke-Railway-Tunnel-2-Geoportal-e1569177330870
Karavanke-Railway-Tunnel-3-Geoportal
previous arrow
next arrow
Investor

MINISTRY OF INFRASTRUCTURE AND SPATIAL PLANNING OF THE REPUBLIC OF SLOVENIA, SLOVENIAN ROADS AGENCY, Tržaška cesta 19, 1000 Ljubljana, tel. +386 14788011

Investment value

INR 936.00 Crore

Project documentation

TENDER DESIGN, FINAL DESIGN, AS BUILT DESIGN

year of completion

Est. 2020

characteristics of the faculty

Challenges and innovation: Challenges faced is time frame for execution of refurbishment since full closure of the track is limited to 180 days. Works include complete replacement of invert fill, reconstruction of inner lining in the most critical parts, excavation of underground chambers and instalment of new equipment.

Basic information:
• Total length of tube: 7975,8 m (Slovenian part: 3602,7 m, Austrian part 4373,1 m
• Area of clearance profile – main tube: 45.16 m2
• Maximal overburden height: 950 m
• Longitudinal gradient: 2,7 ‰– 6,0 ‰